Prequalification in Procurement: World Bank Definition

Under the World Bank Procurement Regulations (7th ed., Sep 2025), prequalification is the shortlisting process that can be used prior to inviting Request for Bids in the procurement of goods, works, or non-consulting services. For large works, customarily more than US$10 million equivalent, or complex works, prequalification is usually necessary and may be mandated in the loan agreement.

Editorial Team

Definition

The World Bank Procurement Regulations (7th edition, September 2025) define prequalification as the shortlisting process that can be used prior to inviting Request for Bids in the procurement of goods, works, or non-consulting services. It functions as a screening stage that narrows the field of potential bidders before competitive bidding begins.

When prequalification is required

The World Bank Standard Prequalification Document sets out thresholds and criteria for when the process applies:

  • For large works, customarily more than US$10 million equivalent, prequalification is usually necessary.
  • For complex works, prequalification is usually necessary regardless of the threshold.
  • Prequalification may be mandated in the loan agreement between the borrower and the Bank.

In practice, this means borrowers procuring major infrastructure or technically demanding works should anticipate a prequalification stage as a standard part of the Request for Bids process, with the requirement potentially embedded directly in financing terms.

Evaluation basis

Prequalification is based on applicants meeting minimum pass-fail criteria, consistent with the World Bank Standard Prequalification Document. This means applicants are assessed against stated minimum requirements rather than scored competitively against one another; those that meet the criteria are shortlisted and invited to submit bids, while those that do not are excluded from the subsequent Request for Bids stage.

Common Questions

What procurement methods can use prequalification?

Prequalification can be used prior to inviting Request for Bids in the procurement of goods, works, or non-consulting services, per the World Bank Procurement Regulations (7th edition, September 2025).

At what contract value is prequalification usually necessary?

For large works, customarily more than US$10 million equivalent, prequalification is usually necessary. It is also usually necessary for complex works, and may be mandated in the loan agreement regardless of value.

How are prequalification applications evaluated?

Prequalification is based on applicants meeting minimum pass-fail criteria. Applicants that satisfy the stated minimum requirements are shortlisted and invited to bid; there is no competitive scoring at this stage.